10-year electricity development plan prepared by national power company PLN and includes demand forecasts, future expansion plans and electricity production forecasts, fuel requirements etc and also indicates the projects that are planned to be developed by PLN and those that are available for Independent Power Producer (IPP) investors (PWC, 2016)
It also includes the Fast Track Program until 2019, which is based on the President's announcement to install 35GW power plants by this year
Targets
- 35GW Programme (additional capacity between 2015 and 2019)
- 20 GW coal-fired power plants
- 13 GW gas-fired power plants
- Renewable capacity: 2.4 GW hydropower, 1.2 GW geothermal, 0.12 GW wind
- RUPTL (install 80.5 GW total additional capacity between 2015 and 2025)